BOLDYN NETWORKS UPS UPGRADES
Project Details
-
Contract Value: $910K
-
Completion Date: February 2023
-
Location: Brooklyn, Queens, Manhattan and the Bronx
-
Scope of Work:
-
Provided wireless coverage across all four major boroughs at 281 stations
-
Removal and replacement of 309 UPS units that required upgrades
-
Replacement of 1,206 batteries that meet their end-of-life cycle
-
Replacement of 2,129 WAGO blocks to improve the reliability and safety of the electrical connections
-