TAP Electric provides clients with excellent project designers and managers, master electricians, and licensed technicians with services ranging from new system designs and installation to upgrades.

 

For each project there is a customized solution to reach the infrastructural stability that all operations need. These strategies were put into action when TAP Electric assisted the Boyce Technologies facility with a complete building electrical renovation and Boingo Wireless with their distributed antenna system.

IMG_7890.png
IMG_7883.png

Brooklyn Navy Yard Building 127

In 1801 the Brooklyn Navy Yard was just that, a Navy Yard. However, in 1970 the land was sold to the City of New York and converted into an industrial park but retained its popular name. Building 127 upgrades include the construction and installation of a new 13.8 KV substation on the second floor of the building. The project includes the provisioning and installation of two medium voltage transformers (750/1000 kVA) and the associated switchgear. To accommodate the new substation, structural steel and concrete work were performed to reinforce the second floor to support the 5 ton transformers and architectural work to house all of the new equipment.

Project Summary

  • Contract Value: $4.5M

  • Completion Date: September 2023

  • Location: Brooklyn, New York

  • Scope of Work:

    • Construction and installation of a new 13.8 KV substation on the second floor

    • Installation of two medium voltage transformers (750/1000 kVA) and the associated switchgear

    • Structural steel and concrete work to reinforce the second floor

    • Architectural work to house all of the new equipment

Boyce Technologies Electrical Renovation

The men and women of Boyce Technologies, Inc. ride the subway. They know exactly how important it is to have easily identifiable, reliable, and easy to use security and communications equipment in the mass transit market. They make products that connect people to the help they need. Boyce couples a broad range of materials and manufacturing processes with decades of experience and knowledge to provide innovative solutions for their customers.

The Boyce facility provides a positive and respectful work environment, and TAP Electric was happy to assist this innovative corporation through a complete building electrical renovation.

Project Summary

  • Contract Value: $350K

  • Completion Date: September 2018

  • Location: Boyce Technologies Facility, Long Island City

  • Scope of Work:

    • Installation of new Con Edison electrical service conduits from the EDR [Switchgear CT Compartment] out to the property line and new main electrical service switchgear

    • Disassembling and cut-out of the existing Con Edison electrical service and switchgear

    • Installation of all switchboards, conduit and conductors for: 

      • 208v to 480v 300kva transformers

      • Respective switchboard

      • Elevators

      • 3 Tru-wire machines

      • 10 Hurco machines

      • 2 Water Jet machines

      • Painting facility

      • Fire Alarm systems

      • RTU HVAC units

      • Welding equipment

Wifi Symbols Over Manhattan
Ethernet Network

Boingo Wireless Distributed Antenna System

Boingo Wireless, Inc. helps the world stay connected as the leading distributed antenna system and Wi-Fi provider. We were proud to assist them with their newest project - Phase 1 of the Boingo Wireless project included the installation of 40 RRU’s for the DAS system between LIRR’s Atlantic terminal and the Bedford Portal in addition to the DAS Head End room at Atlantic Terminal.

 

Phase 2 continued with the installation of an additional 72 DAS RRU’s from the Ralph Ave. Portal to East New York station and continuing on to the Dunton portal. Both phases included the installation of electrical gear to support the RRU’s, fiber, and coax interconnections and testing.

Project Summary

  • Contract Value: $10.8M

  • Completion Date: 2021

  • Location: Brooklyn, New York

  • Scope of Work:

    • Phase 1 of the Boingo Wireless project included the installation of 40 RRU’s for the DAS system between LIRR’s Atlantic terminal and the Bedford Portal in addition to the DAS Head End room at Atlantic Terminal

    • Phase 2 continued with the installation of an additional 72 DAS RRU’s from the Ralph Ave. Portal to East New York station and continuing on to the Dunton portal

    • Both phases included the installation of electrical gear to support the RRU’s, fiber, and coax interconnections and testing