top of page

NYCT MONTAGUE FURMAN SUBSTATION

The NYCT Montague Furman Substation project includes the replacement of high tension switchgear and flood mitigation at the Montague Furman Substation.

  • Contract Value: $4M

  • Completion Date: September 2023

  • Location: Brooklyn, NY

  • Scope of Work:

    • Replacement of two units of the high tension switchgear (rated 27KV) along with the replacement of the low tension switchgear

    • Flood mitigation on this project includes the installation of new steel columns and elevated platforms along with flood doors, flood vents, sump pit, roll-up gate, and flood barriers