NYCT “SANDY” RECOVERY PROJECT JORALEMON TUBE REHABILITATION
This project included the removal and replacement of the positive and negative traction power cables powering the third rail system. The replacement and mitigation of the power equipment in the DC circuit breaker house and substation, antenna system (Fiber Optic and Copper cable), communication system, and emergency alarm/emergency telephone systems.
Project Details
-
Contract Value: $75.5M
-
Completion Date: 2017
-
Location: Brooklyn & Manhattan, NY
-
Scope of Work:
-
Removal and replacement of the positive and negative traction power cables powering the third rail system
-
Replacement of fiber optics, copper, radio antenna cables on messengers and in the duct banks
-
New sound power telephone, emergency alarm and emergency telephone
-
Water leak remediation
-
Installation of watertight doors and concrete columns and beams at Battery Park substation
-
New tunnel lighting
-