NYCT RETROFIT OF 21 EXISTING 25HZ FREQUENCY CONVERTERS AT 11 TRACTION POWER SUBSTATIONS
Project Details
-
Contract Value: $13M
-
Completion Date: June 2021
-
Location: Queens & Manhattan, NY
-
Scope of Work:
-
Retrofit 21 60/25 Hz frequency converters and their controls at ten substations
-
Removals, installation and testing of the new equipment
-
Synchronizing the new equipment to the 25Hz distribution system
-