top of page

TBTA REPLACEMENT OF SWITCHGEAR AND POWER DISTRIBUTION SYSTEM

The TBTA Replacement Of Switchgear and Power Distribution System project included removing and replacing the electrical switchgear and Motor Control Centers (MCCs) throughout the Brooklyn Battery Tunnel to upgrade the Tunnel’s ventilation system. The replacement of dry-type transformers, PMP panel interiors, automatic transfer switches, UPS systems for the tunnel lighting. The removal and replacement of all associated electrical cable and buss-work.

Project Details​

  • Contract Value: $50M

  • Completion Date: 2015

  • Location: Brooklyn Battery Tunnel, NY

  • Scope of Work:

    • Remove and replace the electrical switchgear and Motor Control Centers (MCCs) throughout the Brooklyn Battery Tunnel to upgrade the Tunnel’s ventilation system

    • Replacement of dry-type transformers, PMP panel Interiors, automatic transfer switches, UPS systems for the tunnel lighting 

    • Removal and replacement of all associated electrical cable and buss-work