REPLACEMENT OF SWITCHGEAR AND POWER DISTRIBUTION SYSTEM

Project Details​

  • Contract Value: $49,906,303

  • Completion Date: 2015

  • Location: Brooklyn Battery Tunnel, NY

  • Scope of Work:

    • Remove and replace the electrical switchgear and Motor Control Centers (MCCs) throughout the Brooklyn Battery Tunnel to upgrade the Tunnel’s ventilation system

    • Replacement of dry-type transformers, PMP panel Interiors, automatic transfer switches, UPS systems for the tunnel lighting 

    • Removal and replacement of all associated electrical cable and buss-work